Six Steps to Standard Installation of Concrete Mixing Plant

Mar 11, 2019

The use of concrete mixing plants in the past two years is increasing. Zhengzhou Lianhua has organized the installation process into the following specifications, and hopes to help everyone.
First, the installation of the loading system
Installation of the small-sized mixing station in the rural area. The installation of the conveyor belt conveyor will unfold the finished material belt conveyor from the bend, place the rear frame on the foundation, connect the front and rear frames, and connect the front and rear legs to the conveyor. The diagonal bracing is connected with the lifting lugs on the frame, then the front part of the conveyor is lifted, the front and rear legs and the diagonal braces are connected, and the anchor bolts of the front and rear legs are finally fastened.
Second, the lifting of the mainframe
Mixing the main unit and the powder batching system. Lift the mainframe frame and place it on the foundation to fasten its anchor bolts.
Third, the installation of the finished ingredient warehouse
The installation of the finished storage hopper of the concrete mixing station will lift the finished storage hopper, stand up the legs, and connect the walking platform and the ladder with the finished material storage hopper. The granule batching system is installed on the basis of the granule batching system. The inserting board is connected, the two side slabs are retracted and connected to the inserting board, and then the original aggregate conveyor is unfolded. The rear frame is connected so that the motorized roller is aligned with the center of the mixer head cover and the anchor bolts are finally tightened.
Fourth, the installation of cement powder silo
Installation of the cement silo The components of the cement silo are assembled one by one on the ground, the cement silo is lifted, and the lower cross-support side of the lower silo bracket is oriented toward the powder batching system, the upper and lower silos are fixed, and the anchor bolts are finally fixed.
Five, the installation of the screw feeder
The screw conveyor is installed to lift the screw conveyor, and the screw conveyor ball joint is connected with the cement bin discharge port, so that the discharge port is aligned with the feed port of the powder hopper, and then the conveyor is connected with the cement bin hanger by the wire rope. Ok, finally fix the anchor bolts.
Six, other accessories
Lift the water pump in the proper position and connect the output water pipe. Place the air compressor on the side of the finished hopper, connect the air compressor outlet to the air control box inlet with the air pipe, and connect the air control box outlet to the gas pipe of the cement silo.
The installation of the concrete mixing station must comply with the above requirements to ensure the late operation and production safety of the mixing station! Lianhua mixing plant manufacturers produce all kinds of mixing station equipment, high quality and low price, welcome to come and buy!